City of Fairfax, VA
Home MenuBurke Station Road Sidewalk & Storm Drainage Improvements
Project Description:
-
This project includes the design and construction of 1,100 linear feet of new curb, gutter and sidewalk resulting in pedestrian and drainage improvements on Burke Station Road between Main Street and Stoughton Road.
Project Update:
- Lane closures and alternating one-way traffic with flagmen will be in effect when grading and restoration work is taking place. A specific traffic control notice for paving work will be provided.
Location:
- West side of Burke Station Road between Main Street and Stoughton Road.
Project Schedule:
- Project completed September 2018.
Project Concept Plans:
- Burke Station Rd Concept 1
- Burke Station Rd Concept 2
- Burke Station Rd Concept 3
- Burke Station Rd Concept 4
- Burke Station Rd Grading Plans
- Burke Station Rd Stormwater Design
Project Final Plans:
- Burke Station Rd Final 1
- Burke Station Rd Final 2
- Burke Station Rd Final 3
- Burke Station Rd Final 4
- Burke Station Rd Final 5
Documents for Download:
- Burke Station Road Project Detour Notification (8/2/17)
- Public Hearing Presentation (6/23/15)
- Presentation to City Council (9/2/14)
Existing Condition (North) | ||
Existing Condition (South) |