Fairfax Blvd at Chain Bridge Rd Intersection (Northfax)

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Northfax Intersection

Project Description:

  • Provide road improvements on Chain Bridge Road (Route 123) from Route 29/50 (Fairfax Boulevard) to Eaton Place
  • Widen Chain Bridge Road (Route 123) to six lanes from Route 29/50 (Fairfax Boulevard) to Eaton Place
  • Improve the geometrics (lane alignments) of the roadway approaches for the intersection of Route 29/50 (Fairfax Boulevard) at Chain Bridge Road (Route 123)
  • Improve pedestrian accommodations at all legs of the intersection
  • Make extensive culvert improvements to eliminate roadway flooding caused by the inadequate culvert under Route 123

Project Schedule:

  • Substantial completion by the end of January 2019.
  • Ribbon cutting May 2019
  • A few additional infrastructure items to be completed in the Spring 2019. These include a pipe crossing at Eaton Place, final paving, signal poles at Orchard Street, pavement markings, and punch list items. 
  • VDOT closeout April 2020

Project Plans:

Documents for Download: